When Removing a Caveat Isn’t the End: Recent Supreme Court Guidance

A caveat can be removed by court order if it lacks any proper basis or fails to include the prescribed particulars. However, a recent Supreme Court decision reveals that sometimes the removal of a caveat is only the starting point. Here, the Court went further, using its discretionary powers to manage ongoing disputes and minimise future conflict between the parties.

Under the Real Property Act 1900 (NSW), a caveator must specify the legal or equitable interest claimed (s 74F) and provide the prescribed particulars under the Real Property Regulation 2019 (NSW). Further, the Court may only extend a caveat if satisfied the claim “has or may have substance” (s 74K).

In Al-Jaradat v Ghunmat [2025] NSWSC 1283, a husband lodged a caveat over a jointly owned property following a dispute about the sale process agreed in a financial settlement. Justice Slattery ordered the removal of the caveat because it “suffer[ed] from a material misdescription of substance” and lacked sufficient particulars. Importantly, the Court then imposed several conditions to protect the parties’ interests. To safeguard the husband’s interests, these conditions included giving him security over a replacement property or, alternatively, quarantining part of the sale proceeds to compensate him for the amount in dispute. The Court also directed an expedited costs assessment.

In this case, costs were awarded against the caveators, and the Court exercised its discretion to prevent further disputes, highlighting that caveat litigation does not always only end with removal.

Managing Defects: When Owners Can Engage a New Builder

Providing a builder with the opportunity to address defects is often a practical way for owners and contractors to minimise loss. Crucially, the recent case of Ceerose Pty Ltd v The Owners – Strata Plan No 89074 (‘The Owners‘) [2025] NSWCA 235 reveals that this is not an absolute obligation. 

This case concerned disputes over alleged defects following the completion of a residential apartment building in Sydney. The NSW Court of Appeal held that there is no positive duty on an owner to provide the builder with an opportunity to rectify defects. Rather, it is the builders’ responsibility to show that the owner’s choice to engage a replacement contractor was unreasonable. The Owners had raised concerns over several years about the builder’s ability and willingness to repair the defects. Since prolonged negotiations had stalled, the Court found no basis to conclude that appointing a new builder was unreasonable.

This case shows that if an owner can prove the builder was given an opportunity to fix defects but failed to do so, it can strengthen the owner’s claim to recover the cost of rectification. Conversely, the failure to do so can significantly reduce damages if unnecessary additional expense is incurred by engaging a replacement builder.

NSW Supreme Court Enforces Director’s $3 Million Liability

The case of Delaney Advertising & Media Pty Ltd v Upper Hunter Solar Pty Ltd [2025] NSWSC 1321 involved Mr Williams, the director of a company planning to develop a solar farm in the Hunter Valley, NSW, who had personally guaranteed a $3 million loan taken out by the company. The company ultimately failed to repay the loan and the lender sold the land used as security and sought to recover the remaining debt.

Mr Williams attempted to avoid liability on several grounds. First, he claimed that he would only be liable after other guarantors had been called upon, based on a verbal conversation he described. The Court rejected this, finding his account contradicted by contemporaneous documents. It also noted that his evidence was unreliable, pointing out his false claim of not having received independent legal advice, despite a certificate proving otherwise.

He further argued that he was not liable under the guarantee because it referred to a different loan document than the one the lender actually used, invoking the legal principle that ambiguities between a loan and its guarantee should be interpreted in favor of the guarantor. The Court dismissed this, finding no real doubt that the guarantee clearly applied to the loan provided by the lender.

Finally, Mr Williams contended that the notice of demand was invalid because it required payment in 21 days instead of the 30 days specified in the agreement. The Court held that, despite this technical error, the lender had demonstrated it suffered loss due to the failure to repay the loan, so he remained liable.

Overall, this case underscores the importance of fully understanding guarantees and loan obligations, as courts will enforce them strictly, and technical defenses are unlikely to relieve a guarantor from liability.

NSW Supreme Court Confirms Vendor Entitled to Keep Deposit in Property Sale Dispute

A recent decision of the Supreme Court of New South Wales clarified the binding effect of contract dates and the restrictions on reclaiming deposits when a property sale does not go ahead. Justice Pike’s judgment confirms that the buyer carries the risk of settlement delays and cannot assume automatic return of their deposit.

In Grubisa v Zhou [2025] NSWSC 942, the dispute concerned the sale of a property at Brighton Drive, Bella Vista, NSW. In this case, settlement was required within a set period from the contract date, but the buyer was unable to complete on time. The seller issued a notice to complete and later sought to terminate the contract. The buyer initially sought to enforce the sale and lodged caveats on the property but eventually abandoned that claim and requested the return of the deposit.

The central issue was when the contract became legally binding: the seller argued it was upon the exchange of contracts, while the buyer claimed it only became binding once the deposit bond and statutory certificate were provided. The buyer also sought the return of the deposit under s 55(2A) of the Conveyancing Act 1919 (NSW), arguing it would be unfair for the seller to retain the deposit given that the property had been resold at a higher price and rented out in the meantime.

The Court held that a binding agreement was formed when the contracts were exchanged, regardless of when the deposit documentation or statutory certificates were finalized. It also found that the deposit still functioned as a guarantee for performance, and there was no unfairness sufficient to justify its return.

Accordingly, the buyer’s claim was dismissed, and the seller was entitled to retain the deposit.

Key Takeaways:

  • The contract date is determined by the exchange of executed documents, not subsequent actions such as provision of a deposit or certificates.
  • A deposit functions as a security for performance and will generally not be returned unless it is clearly unjust or inequitable.
  • Parties must ensure timely compliance with settlement obligations and understand that delays in securing funding do not automatically invalidate termination notices.

Supreme Court Confirms a Party Cannot Rely on Its Own Breach to Terminate a Lease

In Alamdo Holdings Pty Ltd v Reece Australia Pty Ltd [2025] NSWSC 946, the Supreme Court of New South Wales affirmed that a party cannot rely on its own breach to terminate a lease. The Court emphasised that this principle is not confined to leases, but applies broadly across all contractual arrangements.

In this case, Alamdo Holdings Pty Ltd (‘Alamdo’) leased commercial premises to Reece Australia Pty Ltd (‘Reece’). Under the lease, Reece was required to secure development approval and an occupation certificate before utilising the premises for its business. Under Article 29(9) of the lease, either party had the right to terminate the lease if the occupation certificate was not issued within six months from the commencement of the lease.

When the certificate had not been granted in this timeframe, Reece attempted to terminate the lease. Alamdo disputed this, arguing that the delay was largely caused by Reece’s own mismanagement of the approval process, including its slow response to Council requests for information, missed payment deadlines, and provision of incomplete or deficient documentation to the Council. Reece argued that it was entitled to terminate regardless of fault, and also raised Alamdo’s outstanding fire safety works as a contributing factor to the delay. 

The Court rejected Reece’s arguments, finding that its failures played a significant role in the delay. The minor outstanding fire safety works on Alamdo’s part did not prevent the Council from processing the development application, so Reece could not claim they were responsible. Accordingly, Reece was not entitled to rely on the termination clause and the lease remained in force. 

This case serves as a clear reminder that a party cannot terminate a contract when its own conduct significantly contributes to the breach. Strict adherence to contractual obligations and procedural requirements is essential, and parties should carefully consider their role in any delay before attempting to rely on a termination right.

Nuisance Damages Claim – Business Disruption

In Transport for NSW v Hunt Leather Pty Ltd; Hunt Leather Pty Ltd v Transport for NSW [2024] NSWCA 227, Sydney CBD business owners along the Sydney Light Rail corridor commenced representative proceedings against Transport for NSW (‘TfNSW‘), alleging that extended construction works – including noise, dust, vibration and restricted access – substantially interfered with their use and enjoyment of land and caused financial loss. The decision provides important clarification of private nuisance principles in the context of major infrastructure projects.

At first instance, the Supreme Court found TfNSW liable in private nuisance for delays beyond an amended construction timetable and awarded damages to some plaintiffs. However, it refused to allow recovery of a 40% litigation funding commission as damages. TfNSW appealed the nuisance finding, and the plaintiffs cross-appealed on the funding issue.

The Court of Appeal unanimously allowed TfNSW’s appeal and overturned the finding of nuisance. It held that the plaintiffs failed to prove that the construction delays amounted to a substantial and unreasonable interference. In particular, the Court held that TfNSW’s Initial Delivery Program could not be treated as a reliable benchmark for unreasonableness, as it could not fully account for practical contingencies such as weather conditions and the discovery of underground utilities. As such, the Court emphasised that construction authorised by statute does not become actionable nuisance merely because it exceeds projected timeframes. In this case, there was insufficient evidence to establish that the actual duration of works, given the complexity of the project and the unknown utilities encountered, was legally unreasonable.

Moreover, the Court dismissed the cross-appeal, confirming that litigation funding commissions are not recoverable as damages. Entering into a funding agreement was a voluntary commercial decision and not a loss caused by any alleged nuisance.

Ultimately, this decision underscores that project delays alone do not establish nuisance. Claimants must demonstrate, with clear evidence, that the interference was substantial and unreasonable in the circumstances. It also reinforces limits on recoverable damages in large-scale infrastructure disputes, particularly in relation to litigation funding costs.

Obligations to Repair Water Leaks in Strata Scheme

In The Owners – Strata Plan No 2661 v Selkirk [2024] NSWSC 760, the NSW Supreme Court considered the respective legal responsibilities of an owners corporation and a lot owner after water leakage caused damage within a Darling Point strata building.

In this case, the owners corporation acknowledged its responsibility under s 106 of the Strata Schemes Management Act 2015 (NSW) (‘the Act’) to repair common property, proposing two repair options limited to the shower area where the defect arose. The lot owner rejected that approach and instead sought complete re-tiling of the bathroom. This disagreement gave rise to a broader dispute concerning both the appropriate scope of works and the amount of rental income allegedly lost while the bathroom remained unusable. Proceedings were ultimately commenced to recover that loss, with the owners corporation disputing liability for the full amount on the basis that the owner’s refusal to allow the proposed repairs affected any entitlement to extended compensation.

The Court accepted the owners corporation’s position, holding that a claim for loss of rent may be reduced where a lot owner’s unreasonable conduct delays or interferes with necessary repair works. Here, the owner’s refusal to provide access, along with her removal of the bathroom tiles without coordination and her mistaken belief that strata insurance would fund the installation of new tiles, delayed the repair process and weakened the connection between the water damage and her claim for ongoing rental loss.

In summary, the decision confirms that an owners corporation bears a strict obligation under s 106 of the Act to repair common property, irrespective of a lot owner’s views on the scope or method of the proposed works. Simultaneously, lot owners must mitigate their loss, and any entitlement to rental compensation may be reduced where their conduct contributes to delay. The Appeal Panel ultimately allowed the appeal and returned the matter to the Tribunal to reconsider both the scope of works required and the amount of rental loss recoverable in the circumstances.

Carrying Out Unapproved Works to Strata Common Property

The decision in Colman v The Owners – Strata Plan 61131 [2025] NSWSC 63 arose from a dispute between a lot owner and the owners corporation of a residential strata scheme in Pyrmont, Sydney.

Initially, the owner’s corporation engaged a contractor to repair a water leak from an expansion joint on the lot owner’s rooftop terrace, which formed part of the common property within the strata scheme. While those repairs were underway, the lot owner separately arranged for the same contractor to undertake additional renovations to the terrace without obtaining prior approval, including removing and replacing tiles and repairing the waterproofing barrier. After those additional works were completed, the lot owner sought retrospective approval by submitting a building application to the strata committee. However, the application was refused as the work could not be classified as minor renovations, and the committee lacked authority to approve works of that scale, which instead require approval by the owner’s corporation at a general meeting prior to commencement.

The lot owner sought to recover the substantial costs of the additional common property and associated lot property work under s 106(5) of the Strata Schemes Management Act 2015 (NSW) (‘the Act’), arguing that the initial repairs authorised by the owner’s corporation were insufficient and that compensation for the independently arranged works was therefore justified. The tribunal dismissed the claim, finding that the waterproofing and tiling works were part of the lot owner’s renovation rather than repairs to a defect in the common property, and therefore were not recoverable as damages under s 106(5) of the Act. It also held that it could not retrospectively approve the works under s 126(2) of the Act because the owner’s corporation were not consulted and couldn’t have refused consent, a decision upheld in subsequent appeal to the NSW Supreme Court.

Failure to obtain the required approval before undertaking works may place lot owners at considerable risk for the following reasons:

  • The owners corporation may apply to NCAT to have the unauthorised works removed and the common property returned to its original condition, at the lot owner’s expense.
  • Costs incurred for unapproved works are generally not recoverable from the owners corporation, even if the works were necessary
  • A lot owner may be responsible for any damage caused to common property or other lots as a result of the unauthorised works.
  • Disputes may result in proceedings before NCAT and potential liability for legal and enforcement costs.
  • Unapproved alterations can create complications when selling a lot and may affect purchaser confidence

Discretion and Reasonableness in Affordable Housing Contribution Conditions

A recent judgment of the Land and Environment Court of NSW in Freecity Alpha Development Pty Ltd v The Council of the City of Sydney [2025] NSWLEC 1694 confirms that affordable housing contribution requirements are not automatic, but subject to statutory discretion and capable of challenge on appeal.

The Environmental Planning and Assessment Act 1979 (NSW) (‘the Act’) confers statutory power on a consent authority to impose a condition requiring either a monetary contribution or the dedication of land for affordable housing where a State environmental planning policy identifies a need in the area. Under the Act, such a condition may only be imposed if it complies with relevant policy requirements (s 7.32(3)(a)), is authorised by an environmental planning instrument, is consistent with an applicable scheme (s 7.32(3)(b)) and is reasonable in the circumstances (s 7.32(3)(c)). In addition, s 7.32(4) requires the consent authority to consider any prior affordable housing contributions made by the applicant.

In this case, the Council of the City of Sydney (‘Council’) proposed to attach a condition of consent requiring an affordable housing contribution to a co-living development intended for use as student accommodation near Sydney University. The Developer challenged the condition under s 7.32(3)(c), arguing that it was unreasonable to require an affordable housing contribution for a development that would operate as student accommodation, which itself provides affordable housing.

Although the State Environmental Planning Policy (Housing) 2021 classifies co-living housing as “Diverse Housing” rather than “Affordable Housing”, when operating as student accommodation it may nevertheless house residents within low-income brackets. As such, the Court held that requiring an additional affordable housing contribution was indeed unnecessary, as the development itself already advances affordable housing objectives.

Ultimately, this judgment does not create a general exemption from affordable housing contributions for co-living developments. However, it reinforces that the reasonableness requirement under s 7.32(3)(c) of the Act is substantive, and that the Court may exercise its discretion to decline to impose such conditions where they operate unreasonably.

NSW Land and Environmental Court Decision – Designing Compliant Projects

The case of Gunnamatta Bay Holdings Pty Ltd v Sutherland Shire Council [2025] NSWLEC 1230 concerned whether a development that fully complied with key Local Environmental Plan (‘LEP’) standards could nonetheless be characterised as an overdevelopment and refused on character grounds.

The developer sought to demolish two existing dwellings and construct seven townhouses on a large waterfront site. The application was permissible within the zoning framework and satisfied all critical development standards under the relevant LEP, including height, floor space ratio and landscaped area, remaining significantly below the maximum density threshold. Despite that compliance, the Council contended the proposal was inconsistent with the site’s low-density character and argued that meeting planning metrics does not necessarily guarantee approval.

In resolving that issue, the Land and Environment Court of NSW reaffirmed how consent authorities must assess development applications and determine compliance with key standards. The Court’s reasoning reflects the statutory framework under the Environmental Planning and Assessment Act 1979. This legislation emphasises that once a development satisfies a numerical control in a development control plan, a council cannot demand more onerous standards (s 4.15(3A)(a)).

This decision is consistent with the principle affirmed by the Chief Judge in Wehbe v Pittwater Council [2007] NSWLEC 827, who stated that “compliance with a development standard is fixed as the usual means by which the relevant environmental or planning objective is able to be achieved” [43]. Where a proposal meets the prescribed controls, there is therefore an expectation that the corresponding objectives – including those relating to desired future character – have been achieved. As such, the Court granted consent, finding that the proposal was not an overdevelopment and aligned with the relevant LEP controls, particularly in the absence of a site-specific desired future character statement.

That said, compliance does not mandate approval in every case. The impacts of a compliant development, such as substantial view loss or heritage harm, may in some circumstances justify refusal. However, the decision indicates that where there are no clear and identifiable adverse impacts, councils will have limited scope to refuse compliant proposals based on broad assertions about character or zone objectives, thereby reducing uncertainty for developers.